The Developer’s Access Letter Now Starts a 60-DayClock: One Year Under the Amended RPAPL § 881

If a developer is building next door, the first thing you usually receive is a certified letter asking for access to your property: a pre-construction survey, crack monitors on your walls, roof protection, a sidewalk shed, sometimes underpinning of your foundation. For decades, many New York property owners handled that letter the same way. They put it in a drawer.

That stopped being a safe strategy on December 5, 2025, when New York rewrote Section 881 of the Real Property Actions and Proceedings Law. As the amended statute approaches its first anniversary, the practical lesson for adjacent owners is clear. Silence no longer protects you. A prompt, well-negotiated response does.

Silence now counts as a refusal

A developer can ask a court for a license to enter your property only after access has been refused. The old statute never said what a refusal was, and an owner who simply did not respond could leave a developer guessing for months.

The amended statute closes that gap. Under § 881(1)(d), access is treated as refused where more than one written notice has been served on the owner by certified mail and has gone unanswered for sixty days. Once that happens, the developer can go to court, and you will be responding to a petition on the court’s schedule instead of negotiating on your own.

Sixty days is not much time. In that window an owner needs to understand what work is proposed, have an engineer look at the plans, and get a written response on the record. A second certified letter is a signal that the clock is already running.

What a court can now order without your consent

The amendment also made the developer’s case easier and broader:

  • A lower threshold. The developer no longer needs to show that access is strictly necessary. It is enough that the work cannot be completed in a commercially reasonable manner without entering your property.
  • A long list of permitted work. The statute now names surveys, monitoring devices, roof and façade protection, scaffolding, sheds, shoring, weatherproofing and temporary projections into your airspace.
  • Underpinning and other structural supports. Courts previously tended to treat underpinning as something a neighbor could simply decline. The statute now lets a court license underpinning, tie-backs, anchors and similar supports where they are required by code, regulation or local law.

In short, “no” is a weaker position than it was a year ago. The owner’s leverage has moved from whether access happens to the terms on which it happens.

What the statute gives adjacent owners

The amendment was not one-sided. A court-ordered license now comes with conditions written into the statute itself:

  • Compensation. The developer must reasonably compensate the adjacent owner for loss of use and enjoyment of the property, including diminution in value (§ 881(4)(e)).
  • Documents before work starts. You are entitled to the relevant plans, surveys, engineering reports and evidence of insurance before the covered work begins.
  • A schedule. The license rests on a good-faith projection of dates and duration. A developer who cannot keep to it has to go back to the court for an extension.
  • Professional fees. A court may require the developer to reimburse the reasonable fees you incur having those documents reviewed (§ 881(5)(b)). The statute does not mention attorneys’ fees by name, but New York courts have long treated reasonable attorney and engineering fees as a proper condition of a license, and have continued to award them since the amendment, including in a Kings County decision this past April. In negotiated agreements, the developer typically agrees to pay them.

The statute is a floor. The agreement is where you are protected.

Here is the part most owners miss. Several of the protections that matter most are not guaranteed by the statute at all:

  • Additional insured status. As first enacted, the amendment required the developer’s liability policy to name the adjacent owner as an additional insured. A follow-up amendment signed February 13, 2026 replaced that with a requirement that the developer provide documentation of its coverage sufficient to let you make a claim. If you want to be an additional insured, and you should, it has to be negotiated into the agreement.
  • Escrow or a bond. The statute contains no requirement that the developer post security for damage or for your fees.
  • Overstay consequences. Projects run late. The statute sends the developer back to court for more time; a negotiated agreement can set a fee that increases the day the license expires.
  • Indemnification, repair standards and monitoring thresholds. These are the terms that decide who pays when a crack appears, and they are drafted, not presumed.

A developer’s form agreement will rarely volunteer any of this. An owner who signs it, or who ignores the letter and lets a court set the terms, generally ends up with the statutory minimum.

What to do when the letter arrives

  • Note the date and keep the envelope. The certified-mail record is the developer’s proof that the clock started. It should be yours too.
  • Respond in writing. A response does not mean consent. It means you are willing to discuss access on appropriate terms, which takes the “silence” argument off the table.
  • Do not sign the developer’s form. It was written by the developer’s lawyer for the developer.
  • Do not let contractors onto the property on a handshake. Informal access gives away your leverage and leaves you without insurance, indemnity or a restoration obligation.
  • Call counsel early. The more of the sixty days that remain, the stronger your negotiating position.

The cost question

Owners often hesitate because they assume protecting themselves will be expensive. In most access matters, the developer needs your cooperation to keep its project on schedule, and courts routinely require developers to bear the adjacent owner’s reasonable attorney and engineering fees. Fee arrangements are addressed at the outset of every matter and depend on the facts.

James J. Corbett, P.C. represents adjacent property owners in RPAPL § 881 access matters throughout New York City and Long Island. If you have received an access request, call 646-470-1107 (New York City) or 516-679-9494 (Long Island).


Attorney Advertising. The material in this blog is meant only to provide general information and is not legal advice. Reading it does not create an attorney-client relationship. Prior results do not guarantee a similar outcome.

The material in this blog is meant only to provide general information and is not a substitute nor is it legal advice to you.